The throughput time was:
A) 4.6 hours
B) 9.7 hours
C) 20.6 hours
D) 16 hours
Throughput Time
The duration required to complete the manufacturing process of a single unit, including all stages of production from raw materials to finished goods.
- Calculate and interpret throughput time.
Verified Answer
VK
Vanika kapoorJun 20, 2024
Final Answer :
B
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.2 hours + 0.2 hours + 3.2 hours + 5.1 hours = 9.7 hours
= 1.2 hours + 0.2 hours + 3.2 hours + 5.1 hours = 9.7 hours
Learning Objectives
- Calculate and interpret throughput time.
Related questions
The Delivery Cycle Time Was
Alghamdi Corporation Keeps Careful Track of the Time Required to ...
During the Most Recent Month at Schwab Corporation, Queue Time ...
Schlarbaum Corporation's Management Keeps Track of the Time It Takes ...
Schurz Corporation's Management Reports That Its Average Delivery Cycle Time ...