The variable overhead efficiency variance for June is:
A) $760 F
B) $760 U
C) $741 F
D) $741 U
Variable Overhead Efficiency Variance
The difference between the expected variable overhead costs based on standard costing and the actual variable overhead incurred, attributable to efficiency.
- Comprehend the theory and arithmetic involved in determining variable overhead rate and efficiency variances.
Verified Answer
FM
Felicia MassonMay 11, 2024
Final Answer :
B
Explanation :
SH = 3,500 units × 0.6 hours per unit = 2,100 hours
Variable overhead efficiency variance = (AH - SH)× SR
= (2,290 hours − 2,100 hours)× $4.00 per hour
= (190 hours)× $4.00 per hour
= $760 U
Variable overhead efficiency variance = (AH - SH)× SR
= (2,290 hours − 2,100 hours)× $4.00 per hour
= (190 hours)× $4.00 per hour
= $760 U
Learning Objectives
- Comprehend the theory and arithmetic involved in determining variable overhead rate and efficiency variances.
Related questions
The Variable Overhead Efficiency Variance for October Is ...
The Variable Overhead Rate Variance for July Is ...
The Variable Overhead Rate Variance for the Month Is Closest ...
The Variable Overhead Rate Variance for August Is ...
Sakelaris Corporation Makes a Product with the Following Standard Costs ...