Asked by Deviu Bhandari on Jun 04, 2024
Verified
To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have predecessor activities.
Early Start Dates
The earliest possible point in time when the activities of a project can begin, taking into account all constraints and preceding tasks.
Predecessor Activities
Tasks that must be completed before a subsequent task can begin, establishing a sequence in project scheduling.
- Understand the process of calculating early start dates based on project start dates.
Verified Answer
SL
Sydney LeightonJun 05, 2024
Final Answer :
False
Explanation :
To calculate early start dates, you begin with the project start date and assign that date as the start date of activities that do not have predecessor activities. Activities with predecessors cannot start until their predecessors are completed.
Learning Objectives
- Understand the process of calculating early start dates based on project start dates.
Related questions
Using the Following Data, Calculate the Beginning Work in Process ...
The Balance of the Finished Goods Inventory at the End ...
The Network Below Represents a Project Being Analyzed by Critical ...
If 180000 Units Are Transferred Out of a Department There ...
Total Units to Be Accounted for Less Units in Beginning ...