To calculate early start dates, begin with the project start date and assign that date as the start date of activities that have predecessor activities.

Early Start Dates

The earliest possible point in time when the activities of a project can begin, taking into account all constraints and preceding tasks.

Predecessor Activities

Tasks that must be completed before a subsequent task can begin, establishing a sequence in project scheduling.

  • Understand the process of calculating early start dates based on project start dates.
verifed

Verified Answer

SL
Sydney LeightonJun 05, 2024
Final Answer :
False
Explanation :
To calculate early start dates, you begin with the project start date and assign that date as the start date of activities that do not have predecessor activities. Activities with predecessors cannot start until their predecessors are completed.