To track your team's progress toward completing an important project,you should use

A) an organizational chart.
B) a Gantt chart.
C) a pie chart.
D) a pictogram.

Gantt Chart

The best-known type of timeline chart.

Organizational Chart

A diagram that shows the structure of an organization and the relationships and relative ranks of its parts and positions/jobs.

Project

A planned set of interrelated tasks to be executed over a fixed period and within certain cost and other limitations.

  • Identify fitting graphical tools for a range of data presentation scenarios.
verifed

Verified Answer

EB
Elizabeth Boatright2 days ago
Final Answer :
B
Explanation :
A Gantt chart is the best choice for tracking a team's progress towards completing a project. It provides a visual representation of the project timeline, including specific tasks and milestones, and allows team members to see their progress towards completing each stage of the project. This makes it easy to identify what tasks are on schedule, what tasks are falling behind, and what tasks may need to be adjusted or prioritized to ensure timely completion of the project.