Asked by Khánh Tr??ng on Jun 21, 2024
Verified
What does the "C" in Deming's PDCA cycle stand for?
A) Compromise
B) Consistency
C) Capacity
D) Check
E) Control
Compromise
A resolution or settlement of a disagreement achieved by both parties making compromises.
Consistency
The quality of achieving a uniform, standard level of performance or behavior over time.
Capacity
The maximum amount that something can contain or produce, often related to production or processing facilities.
- Identify and implement the PDCA cycle within ongoing enhancement procedures.
Verified Answer
SB
sheba baidooJun 24, 2024
Final Answer :
D
Explanation :
The "C" in Deming's PDCA cycle stands for "Check." The cycle consists of Plan, Do, Check, and Act, with each step building upon the previous one to continually improve processes and outcomes.
Learning Objectives
- Identify and implement the PDCA cycle within ongoing enhancement procedures.