When building a house or constructing an airplane that must be completed by a certain date, which type of scheduling should be used?
A) forward scheduling
B) backward scheduling
C) horizontal scheduling
D) vertical scheduling
Backward Scheduling
A planning method that starts with the end goal or deadline and works backwards to determine the timing of preceding activities.
Constructing Airplane
The engineering and assembling processes involved in building aircraft.
Certain Date
A specific, identified day in the calendar on which an event is scheduled to take place or a deadline is set.
- Identify different methods of scheduling and understand their significance in improving productivity and effectiveness.
Verified Answer
Learning Objectives
- Identify different methods of scheduling and understand their significance in improving productivity and effectiveness.
Related questions
The Detailed Breakdown of Information Explaining How the Product or ...
In an Effort to Increase Productivity, Some Service Businesses Like ...
When Materials and Resources Are Allocated for Production When the ...
What Type of Scheduling Device Enables a Small Business Owner ...
When Production Activities Are Arranged Around the Due Date for ...