When graphing cost-volume-profit data on a CVP chart:

A) Units are plotted on the horizontal axis; costs on the vertical axis.
B) Units are plotted on the vertical axis; costs on the horizontal axis.
C) Both units and costs are plotted on the horizontal axis.
D) Both units and cost are plotted on the vertical axis.
E) Data points always represent expected future points.

CVP Chart

A graphical representation used in Cost-Volume-Profit analysis to show the effects of different levels of volume and cost on operating profits.

Cost-Volume-Profit Data

Information that shows how changes in cost and volume affect a company's profit, used for making short-term economic decisions.

  • Analyze cost-volume-profit (CVP) diagrams and comprehend their importance.
verifed

Verified Answer

JW
Jacob WilliamsJul 20, 2024
Final Answer :
A
Explanation :
EA) In a CVP chart, units are typically plotted on the horizontal (x) axis, and costs (both fixed and variable) are plotted on the vertical (y) axis. This setup allows for the visualization of how costs change with different levels of production or sales volume.E) CVP analysis is forward-looking and is used for planning and decision-making purposes. Therefore, the data points on a CVP chart represent expected or projected future amounts, not historical data.