When production activities are arranged around the due date for product completion, which of the following types of scheduling is used?
A) forward scheduling
B) backward scheduling
C) horizontal scheduling
D) vertical scheduling
Due Date
The specific day by which something is due or expected to be completed, such as a payment or assignment.
Product Completion
The final stage in the production process where a product is finished and ready for sale.
Backward Scheduling
Scheduling that involves arranging production activities around the due date for the product.
- Understand a range of scheduling approaches and their contribution to the enhancement of efficiency and effectiveness.
Verified Answer
NT
Ngoc Tram NguyenMay 03, 2024
Final Answer :
B
Explanation :
Backward scheduling starts with the due date for a product and schedules the necessary production activities in reverse order to determine when the production process should start. This method ensures that the product is completed on time.
Learning Objectives
- Understand a range of scheduling approaches and their contribution to the enhancement of efficiency and effectiveness.
Related questions
When Building a House or Constructing an Airplane That Must ...
What Type of Scheduling Device Enables a Small Business Owner ...
The Detailed Breakdown of Information Explaining How the Product or ...
When Materials and Resources Are Allocated for Production When the ...
In an Effort to Increase Productivity, Some Service Businesses Like ...