Which critical ratio value implies that a job is already late?
A) more than 100
B) 1
C) less than 1
D) 10
E) 110
Job
A paid position of regular employment or a specific task done as part of the routine of one's occupation.
- Discern and appreciate the various principles governing job sequencing and dispatching.
Verified Answer
BM
brandy martinMay 02, 2024
Final Answer :
C
Explanation :
The critical ratio is calculated by dividing the time remaining until the due date by the time required to complete the job. If the critical ratio is less than 1, the job is already late. Therefore, choice C is the correct option.
Learning Objectives
- Discern and appreciate the various principles governing job sequencing and dispatching.
Related questions
Which of the Following Dispatching Rules Tends to Minimize Job ...
Which of the Following Are Limitations of Rules-Based Dispatching Systems ...
________ Is the Assignment of Jobs to Work or Processing ...
Five Jobs Are Waiting to Be Processed A) C, E, ...
The Priority Rule That Sequences Jobs Using the Smallest Ratio ...