Which of the following occurs when the promisor indicates before the time for his performance that he is unwilling or unable to carry out the contract?
A) Anticipatory repudiation
B) Waiver
C) Estoppel
D) Accord and satisfaction
Anticipatory Repudiation
Occurs when one party indicates by words or actions that they will not fulfill their contractual obligations in the future.
- Contrast anticipatory repudiation with the actual breach of a contract.
Verified Answer
CK
Crave KhemicalJun 19, 2024
Final Answer :
A
Explanation :
One type of breach of contract occurs when the promisor indicates before the time for his performance that he is unwilling or unable to carry out the contract.This is called anticipatory repudiation or anticipatory breach.Anticipatory breach generally constitutes a material breach of contract that discharges the promisee from all further obligation under the contract.
Learning Objectives
- Contrast anticipatory repudiation with the actual breach of a contract.
Related questions
When an Anticipatory Repudiation Occurs,what Must the Nonbreaching Party Show ...
Bing Engaged Dill to Perform Personal Services for $2,200 a ...
Justin Agrees to Start a Life-Size Portrait of Julia Beginning ...
A(n)________ Occurs Whenever a Party Fails to Perform Her Obligations ...
A Breach Occurs Whenever a Party Fails to Perform Her ...