Asked by Yating Zhong on May 12, 2024

verifed

Verified

Which of the following statements regarding finite capacity scheduling (FCS) is false?

A) Finite capacity scheduling allows delivery needs to be balanced against efficiency.
B) Finite capacity scheduling overcomes the disadvantages of systems based exclusively on rules.
C) Finite capacity scheduling allows virtually instantaneous change by operators.
D) Finite capacity scheduling software formalizes the same data needed in any manual system.
E) None; all of the above are true.

Finite Capacity Scheduling

Finite Capacity Scheduling is a planning method that takes into account the limited resources (such as machinery or workforce) available to complete tasks within a given timeframe.

Instantaneous Change

A rapid or sudden shift in conditions, values, or states, often used in mathematics and physics to describe changes occurring at a specific point in time.

Manual System

A system or process performed by human effort rather than by using digital tools or automation.

  • Understand the principles and applications of finite capacity scheduling (FCS) in various environments.
verifed

Verified Answer

SP
Sarah PaytonMay 15, 2024
Final Answer :
E
Explanation :
All the statements provided about finite capacity scheduling (FCS) are true. FCS indeed balances delivery needs with efficiency, overcomes the limitations of rule-based systems, allows for quick changes by operators, and formalizes data necessary for both manual and automated systems.