Asked by Fabian Macias on Sep 26, 2024

verifed

Verified

Which of these does a PERT activity represent?

A) The critical path
B) Completed steps
C) Wasted time
D) A performance milestone
E) Work in process

PERT Activity

A task or event within the Program Evaluation and Review Technique, a project management tool used to schedule, organize, and coordinate tasks within a project.

Critical Path

The sequence of stages determining the minimum time needed to complete a project, where any delay in the stages causes a delay in the project.

  • Understand the significance and uses of project management instruments such as Gantt charts, PERT networks, and flow charts in the organization and implementation of projects.
verifed

Verified Answer

NS
Nicholas Sales3 days ago
Final Answer :
E
Explanation :
A PERT activity represents work in process, meaning the steps or tasks that are currently in progress towards the completion of a project. The critical path is a sequence of activities that must be completed in a specific order and is represented in a PERT chart as a series of connected activities. Completed steps and wasted time are not represented in a PERT chart as they do not contribute to the future progress of the project. A performance milestone is a significant achievement or goal in a project but is not specific to the PERT chart representation of project tasks.