Which portion of the master production schedule is normally fixed, frozen, or firm?
A) the entire schedule
B) only the aggregate schedule
C) only the middle of the schedule
D) only the near-term portion
E) only the far-term portion
Master Production Schedule
is a plan for individual commodities to be produced in each time period, including quantity, production start, and end dates.
- Familiarize oneself with the principles of master production scheduling and its execution in assorted operation types.
Verified Answer
DJ
Danielle JeanaeMay 21, 2024
Final Answer :
D
Explanation :
The near-term portion of the master production schedule (typically the first few weeks or months) is generally fixed, frozen, or firm, as it is closest to the current date and has already been planned and committed to production. The far-term portion may still be subject to change based on changes in demand, supply chain disruptions, or other unforeseen factors. Therefore, option D is the best choice.
Learning Objectives
- Familiarize oneself with the principles of master production scheduling and its execution in assorted operation types.
Related questions
In Continuous (Stock-To-Forecast) Operations, the Master Production Schedule Is Usually ...
A Document Calls for the Production of 50 Small Garden ...
In Job Shop (Make-To-Order) Operations, the Master Production Schedule Is ...
A Master Production Schedule Contains Information About ...
The ________ Is (Are) the MRP Input Detailing Which End ...