Which scheduling technique should be employed when due dates are important for a job order?
A) forward scheduling
B) loading
C) dispatching
D) backward scheduling
E) master scheduling
Due Dates
The specified dates by which something is to be completed or submitted.
Job Order
A work order issued for the production of a specific quantity of a product or the performance of a specific service.
Backward Scheduling
Scheduling that begins with the due date and schedules the final operation first and the other job steps in reverse order.
- Comprehend the fundamentals of forward and backward scheduling and their practical applications.
Verified Answer
TD
Tabatha Delgado7 days ago
Final Answer :
D
Explanation :
Backward scheduling is the technique where the due date of the job order is fixed and the schedule is planned backwards from this date to determine the start date of the production process. This ensures that the job is completed on or before the due date.
Learning Objectives
- Comprehend the fundamentals of forward and backward scheduling and their practical applications.
Related questions
Process-Focused Facilities and Repetitive Facilities Generate Forward-Looking Schedules, but Process-Focused ...
Earliest Due Date Is a Shop Floor Dispatching (Sequencing) Rule ...
Forward Scheduling Is the Scheduling of ...
Forward Scheduling ...
In Forward Scheduling, Jobs Are Scheduled as Late as Possible ...