A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.
A) There are two paths in this network.
B) There are four paths in this network.
C) There are five paths in this network.
D) There are 25 paths through this network.
E) There is no critical path in this network.
CPM Network
A project management tool that models tasks, timelines, and dependencies within a project as a network, standing for Critical Path Method.
Immediate Predecessor
In project management, refers to an activity that must be completed directly before another specific activity can commence.
Network Paths
Sequences of connected nodes and links in a network diagram, representing possible routes through a project schedule or communication framework.
- Absorb the essence and application of critical path analysis in project development and management.
Verified Answer
Learning Objectives
- Absorb the essence and application of critical path analysis in project development and management.
Related questions
A Simple CPM Network Has Three Activities, D, E, and ...
The Critical Path for the Network Activities Shown Below Is ...
Which of the Following Statements Concerning CPM Activities Is False ...
The Network Below Represents a Project Being Analyzed by Critical ...
Given the Project Within the Table Below CalculateA ...