During the most recent month at Schwab Corporation, queue time was 7.8 days, inspection time was 0.3 day, process time was 1.3 days, wait time was 9.7 days, and move time was 0.7 day.Required:a. Compute the throughput time.b. Compute the manufacturing cycle efficiency (MCE).c. What percentage of the production time is spent in non-value-added activities?d. Compute the delivery cycle time.
Throughput Time
The complete duration needed to create a product, starting from the commencement of its production until it's finished.
Manufacturing Cycle Efficiency
A metric that evaluates the efficiency of a manufacturing process by comparing the value-added time to the total production time.
Queue Time
The duration that an item spends waiting to be processed or serviced in a system.
- Calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time in the context of quality and performance management.
- Identify non-value added activities in manufacturing and propose methods to reduce them.
Verified Answer
Learning Objectives
- Calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time in the context of quality and performance management.
- Identify non-value added activities in manufacturing and propose methods to reduce them.
Related questions
Schurz Corporation's Management Reports That Its Average Delivery Cycle Time ...
Alghamdi Corporation Keeps Careful Track of the Time Required to ...
Schlarbaum Corporation's Management Keeps Track of the Time It Takes ...
The Manufacturing Cycle Efficiency (MCE)was Closest To
What Is the Manufacturing Cycle Efficiency