Finite capacity scheduling, unlike MRP, recognizes the capacity limitations of departments and machines when building schedules.
Finite Capacity Scheduling
A detailed planning method that ensures production activities are scheduled within the constraints of available resources and capacity.
MRP
Material Requirements Planning, a system for managing manufacturing processes by calculating materials, components, and schedule needs.
- Comprehend the difference between finite capacity scheduling and MRP in terms of capacity considerations.
Verified Answer
ZK
Zybrea KnightMay 08, 2024
Final Answer :
True
Explanation :
Finite capacity scheduling takes into account the availability and capacity of resources such as departments and machines when creating schedules, whereas MRP focuses mainly on material planning and inventory control.
Learning Objectives
- Comprehend the difference between finite capacity scheduling and MRP in terms of capacity considerations.
Related questions
The Word Infinite in Infinite Capacity Scheduling Refers to the ...
The Constant Work-In-Process (ConWIP) Card Aids Input-Output Control by Limiting ...
Finite Capacity Scheduling Allows Virtually Instantaneous Changes by Operators, Which ...
Conventional MRP Uses Time Buckets That Do Not Recognize Capacity ...
Describe Finite Capacity Scheduling in a Sentence or Two ...