Asked by Drishana Pillay on May 22, 2024

verifed

Verified

Hermansen Corporation produces large commercial doors for warehouses and other facilities. In the most recent month, the company budgeted production of 5,100 doors. Actual production was 5,400 doors. According to standards, each door requires 3.8 machine-hours. The actual machine-hours for the month were 20,880 machine-hours. The standard supplies cost is $7.90 per machine-hour. The actual supplies cost for the month was $152,063. Supplies cost is an element of variable manufacturing overhead. The variable overhead efficiency variance for supplies cost is:

A) $10,045 Favorable
B) $10,045 Unfavorable
C) $2,844 Favorable
D) $2,844 Unfavorable

Variable Overhead Efficiency Variance

This is the difference between the actual hours taken to produce something and the standard hours expected, multiplied by the variable overhead rate per hour.

Supplies Cost

The cost associated with materials and items that are consumed or used in the process of producing goods or providing services.

Machine-Hours

A measure of production output or capacity based on the number of hours a machine operates.

  • Undertake the task of calculating and investigating the disparities in variable overhead, especially rate and efficiency variances.
verifed

Verified Answer

JS
Jashanpal Singh BajwaMay 26, 2024
Final Answer :
D
Explanation :
The variable overhead efficiency variance is calculated as (Actual Machine-Hours - Standard Machine-Hours) x Standard Rate. The standard machine-hours for actual production are 5,400 doors x 3.8 hours/door = 20,520 hours. The difference between actual machine-hours (20,880) and standard machine-hours (20,520) is 360 hours. The standard rate is $7.90 per machine-hour. Therefore, the variance is 360 hours x $7.90/hour = $2,844 Unfavorable, because actual hours exceeded standard hours.