Asked by Yenill Jacalan on May 18, 2024

verifed

Verified

Warp Manufacturing Corporation uses a standard cost system for the production of its ski lift chairs. Warp uses machine-hours as an overhead base. The variable manufacturing overhead standards for each chair are 1.2 machine-hours at a standard cost of $18 per hour. During the month of September, Warp incurred 34,000 machine-hours in the production of 32,000 ski lift chairs. The total variable manufacturing overhead cost was $649,400. What is Warp's variable overhead rate variance for September?

A) $37,400 Unfavorable
B) $41,800 Favorable
C) $79,200 Favorable
D) $84,040 Favorable

Variable Overhead Rate Variance

The difference between the actual variable overhead rate incurred and the standard rate, multiplied by the actual activity level.

Standard Cost

The predetermined cost of manufacturing a single unit or a number of units during a specific period under normal conditions.

  • Proceed with the calculation and analysis of variable overhead inconsistencies, with particular attention to rate and efficiency variances.
verifed

Verified Answer

KG
Kabir GandhiwadiMay 24, 2024
Final Answer :
A
Explanation :
The variable overhead rate variance is calculated as the difference between the actual cost per hour and the standard cost per hour, multiplied by the actual hours worked. The standard cost for the variable manufacturing overhead is $18 per hour. The actual cost per hour can be calculated as the total variable manufacturing overhead cost divided by the actual machine-hours, which is $649,400 / 34,000 = $19.1 per hour. The rate variance is then ($19.1 - $18) * 34,000 = $1.1 * 34,000 = $37,400 Unfavorable, because the actual cost per hour is higher than the standard cost per hour.