____ is a feature of Gantt charts that is an improvement over flow charts.

A) Separate steps
B) Formally written objectives
C) Budget estimates
D) Time element
E) Staffing requirements

Time Element

A factor considering the duration or specific period within which certain activities or processes are expected to occur or be completed.

Gantt Charts

A type of bar chart that illustrates a project schedule, showing the start and finish dates of the various elements and tasks within the project.

  • Identify the essentiality and practicality of project management mechanisms such as Gantt charts, PERT networks, and flow charts in the planning and realization of projects.
verifed

Verified Answer

KS
karen seiffertabout 14 hours ago
Final Answer :
D
Explanation :
The time element is a feature of Gantt charts that is not typically found in flow charts. Gantt charts show the timeline for each task or activity, allowing for a visual representation of the order and duration of tasks. This makes it easier to understand the project schedule and track progress over time.