Navern Corporation manufactures and sells custom home elevators.From the time an order is placed until the time the elevator is installed in the customer's home averages 90 days.This 90 days is spent as follows: Navern Corporation manufactures and sells custom home elevators.From the time an order is placed until the time the elevator is installed in the customer's home averages 90 days.This 90 days is spent as follows:   What is Navern's manufacturing cycle efficiency (MCE) for its elevators? A) 20.0% B) 36.0% C) 45.0% D) 64.0% What is Navern's manufacturing cycle efficiency (MCE) for its elevators?

A) 20.0%
B) 36.0%
C) 45.0%
D) 64.0%

Manufacturing Cycle Efficiency (MCE)

A metric that identifies the proportion of total manufacturing cycle time that is value-added, aiming to improve process efficiency.

Custom Home Elevators

Elevators that are specifically designed and built to fit the unique requirements of a residential home.

  • Comprehend and compute the efficiency of the manufacturing cycle (MCE).
verifed

Verified Answer

ZK
Zybrea KnightJun 07, 2024
Final Answer :
B
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 18 days + 2 days + 20 days + 10 days = 50 days
MCE = Value-added time (Process time)÷ Throughput (manufacturing cycle)time
= 18 days ÷ 50 days = 36%