Navern Corporation manufactures and sells custom home elevators.From the time an order is placed until the time the elevator is installed in the customer's home averages 90 days.This 90 days is spent as follows: What is Navern's manufacturing cycle efficiency (MCE) for its elevators?
A) 20.0%
B) 36.0%
C) 45.0%
D) 64.0%
Manufacturing Cycle Efficiency (MCE)
A metric that identifies the proportion of total manufacturing cycle time that is value-added, aiming to improve process efficiency.
Custom Home Elevators
Elevators that are specifically designed and built to fit the unique requirements of a residential home.
- Comprehend and compute the efficiency of the manufacturing cycle (MCE).
Verified Answer
ZK
Zybrea KnightJun 07, 2024
Final Answer :
B
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 18 days + 2 days + 20 days + 10 days = 50 days
MCE = Value-added time (Process time)÷ Throughput (manufacturing cycle)time
= 18 days ÷ 50 days = 36%
= 18 days + 2 days + 20 days + 10 days = 50 days
MCE = Value-added time (Process time)÷ Throughput (manufacturing cycle)time
= 18 days ÷ 50 days = 36%
Learning Objectives
- Comprehend and compute the efficiency of the manufacturing cycle (MCE).
Related questions
Hunt Company Has the Following Production Data: the Manufacturing ...
The Manufacturing Cycle Efficiency (MCE)was Closest To
During the Most Recent Month at Schwab Corporation, Queue Time ...
Schlarbaum Corporation's Management Keeps Track of the Time It Takes ...
Alghamdi Corporation Keeps Careful Track of the Time Required to ...