Asked by elizabeth mccloskey on May 20, 2024

verifed

Verified

The manufacturing cycle efficiency (MCE) was closest to:

A) 0.89
B) 0.06
C) 0.29
D) 0.12

Manufacturing Cycle Efficiency

A measure of the efficiency in manufacturing, calculated as the ratio of value-added production time to total cycle time.

  • Calculate and understand manufacturing cycle efficiency (MCE).
verifed

Verified Answer

CC
Camila ChavesMay 24, 2024
Final Answer :
D
Explanation :
Throughput time = Process time + Inspection time + Move time + Queue time
= 1.2 hours + 0.2 hours + 3.2 hours + 5.1 hours = 9.7 hours
MCE = Value-added time (Process time)÷ Throughput (manufacturing cycle)time
= 1.2 hours ÷ 9.7 hours = 0.124
Reference: CH10-Ref22
The management of International Cookwares believes that delivery performance measures must be improved if the company is to maintain its competitive edge.The following data are considered to be typical of the time to complete orders.
• Process time: 4 days
• Wait time to the start of production: 15 days
• Move time: 3 days
• Inspection time: 2 days
• Queue time during the production process: 8 days