Asked by Teigan Catlin on Jul 25, 2024
Verified
The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
PERT Pessimistic Time
In the PERT project management technique, it is the longest time that a task is expected to take, considering potential delays and assuming that everything goes wrong.
Minimum Time
The shortest possible time in which a process or task can be completed, often considered in project planning and efficiency studies.
- Understand the consequences of task duration on project timelines and the essential route.
Verified Answer
FE
Falon EvansJul 27, 2024
Final Answer :
False
Explanation :
The PERT pessimistic time estimate is an estimate of the maximum time an activity will require, not the minimum. The minimum time estimate is the optimistic time estimate.
Learning Objectives
- Understand the consequences of task duration on project timelines and the essential route.
Related questions
The Standard Deviation of Project Duration Is the Average of ...
Given the Project Within the Table Below CalculateA ...
The Network Below Represents a Project Being Analyzed by Critical ...
If Any Activity on the Critical Path Is Delayed, the ...
The Longest Path to the Completion of the Project Is ...