There are 5 jobs (A, B, C, D, E) that need to be completed in a work centre. The due dates are the 10th, 13th, 8th, 20th, and 15th respectively with process times of 7, 12, 7, 20, and 10 respectively as well. If today is the 1st of the month calculate the critical ratio for each and use this value to sequence the jobs in the order they should be started.
The reasons for buying in the make-or-buy decision include freeing management to focus on primary business; lower acquisition cost; preserve supplier commitment; obtain technical or managerial ability; inadequate capacity; reduce inventory costs; ensure alternative sources of supply; inadequate managerial or technical resources; reciprocity; and item is protected by patent or trade secret.