Which of the following is an aid used to monitor jobs in process?
A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Pareto chart
Gantt Schedule Chart
A type of bar chart that illustrates a project schedule, showing the start and finish dates of the various components and elements of a project.
Monitoring Jobs
Involves the continuous observation and tracking of job progress and performance to ensure that it aligns with planned objectives and schedules.
Process Aid
denotes tools, materials, or information used to support and streamline operational processes, enhancing efficiency and effectiveness in production or administrative tasks.
- Evaluate the criteria for effective scheduling.
Verified Answer
Learning Objectives
- Evaluate the criteria for effective scheduling.
Related questions
Which of the Following Is Not an Effectiveness Criterion for ...
The Three Components That Can Lead to Competitive Advantage Through ...
Which of the Following Is Not a Key Benefit from ...
What Type of Scheduling Device Enables a Small Business Owner ...
When Building a House or Constructing an Airplane That Must ...