Which of the following is an aid used to monitor jobs in process?

A) a Gantt load chart
B) the assignment method
C) a Gantt schedule chart
D) Johnson's rule
E) a Pareto chart

Gantt Schedule Chart

A type of bar chart that illustrates a project schedule, showing the start and finish dates of the various components and elements of a project.

Monitoring Jobs

Involves the continuous observation and tracking of job progress and performance to ensure that it aligns with planned objectives and schedules.

Process Aid

denotes tools, materials, or information used to support and streamline operational processes, enhancing efficiency and effectiveness in production or administrative tasks.

  • Evaluate the criteria for effective scheduling.
verifed

Verified Answer

NI
Nimra IshtiaqJun 08, 2024
Final Answer :
C
Explanation :
A Gantt schedule chart is specifically designed to monitor jobs in process and track progress over time. It displays the start and end dates of tasks and can also show dependencies between tasks. The other options provided (Gantt load chart, assignment method, Johnson's rule, Pareto chart) are not specifically designed for job monitoring and may not provide the same level of detail and tracking capabilities as a Gantt schedule chart.