Asked by Nefetiti Easter on Jun 13, 2024

verifed

Verified

Gutknecht Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity-based costing system: Gutknecht Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity-based costing system:   Distribution of resource consumption:   How much cost, in total, would be allocated in the first-stage allocation to the Other activity cost pool? A)  $138,000 B)  $210,000 C)  $180,000 D)  $216,000 Distribution of resource consumption:
Gutknecht Corporation uses an activity-based costing system with three activity cost pools. The company has provided the following data concerning its costs and its activity-based costing system:   Distribution of resource consumption:   How much cost, in total, would be allocated in the first-stage allocation to the Other activity cost pool? A)  $138,000 B)  $210,000 C)  $180,000 D)  $216,000 How much cost, in total, would be allocated in the first-stage allocation to the Other activity cost pool?

A) $138,000
B) $210,000
C) $180,000
D) $216,000

Resource Consumption

The amount of resources used during a process, such as raw materials, energy, or labor.

  • Gain an understanding of primary and secondary allocations within Activity-Based Costing.
  • Acknowledge the importance of cost pools in Activity-Based Costing and their effect on allocating costs.
verifed

Verified Answer

SC
Suléze CronjéJun 18, 2024
Final Answer :
B
Explanation :
To allocate costs in the first stage, we need to add up the total overhead costs and allocate them based on the activity cost drivers.

Total overhead costs = $1,470,000 + $600,000 + $330,000 = $2,400,000

Allocating costs to Other activity cost pool:

Other cost driver rate = $600,000 / 3,000 machine-hours = $200 per machine-hour

Activity consumption for Other = 900 machine-hours

Cost allocated to Other = $200 per machine-hour x 900 machine-hours = $180,000

Thus, the total cost allocated to the Other activity cost pool in the first-stage allocation is $180,000. Therefore, the best choice is B.