Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:   The manufacturing cycle efficiency (MCE)  was closest to: A)  0.46 B)  0.06 C)  0.20 D)  0.19 The manufacturing cycle efficiency (MCE) was closest to:

A) 0.46
B) 0.06
C) 0.20
D) 0.19

Manufacturing Cycle Efficiency

A measure of the effectiveness of a manufacturing process, calculated by dividing the value-added production time by the total cycle time.

Fill Orders

The process of completing customer requests for goods or services in accordance with purchase agreements or specifications.

  • Gain an understanding of the manufacturing cycle efficiency (MCE) concept and the procedures for its computation.
verifed

Verified Answer

RP
Rachael PaleyJul 29, 2024
Final Answer :
C
Explanation :
The manufacturing cycle efficiency (MCE) formula is:
MCE = (Value-added time / Total manufacturing time) x 100%

Value-added time is the time spent actually adding value to the product, while total manufacturing time is the entire time required to manufacture the product.

In this case, the value-added time is 4.5 hours (assembly time + inspection time), and the total manufacturing time is 22.5 hours (assembly time + inspection time + waiting time).

Using the formula, we get:
MCE = (4.5 / 22.5) x 100%
MCE = 0.2 or 20%

Therefore, the closest option is C) 0.20.