Asked by Anthony Vasquez on Jun 17, 2024
Verified
Vandenheuvel Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: The manufacturing cycle efficiency (MCE) was closest to:
A) 0.34
B) 0.20
C) 0.26
D) 0.16
Manufacturing Cycle Efficiency
The ratio of value-added time to total throughput time in a manufacturing process, measuring the efficiency of production.
Fill Orders
The process of completing customer requests for goods by preparing and dispatching products.
- Acquire knowledge on the concept and calculation of manufacturing cycle efficiency (MCE).
Verified Answer
JR
Jenny ReyesJun 22, 2024
Final Answer :
C
Explanation :
Manufacturing cycle efficiency (MCE) can be calculated using the formula:
MCE = Value-added time / Total manufacturing time
Value-added time in this case is the time spent actually working on the order, which is the sum of the times for cutting, drilling, machining, and assembly:
Value-added time = 1.5 + 0.8 + 0.6 + 1.2 = 4.1 hours
Total manufacturing time is the sum of the value-added time and the non-value-added time (i.e. time spent waiting or in transit):
Total manufacturing time = 4.1 + 1.5 + 0.6 = 6.2 hours
Using these numbers, we can calculate the MCE:
MCE = 4.1 / 6.2 ≈ 0.26
Therefore, the closest answer is C) 0.26.
MCE = Value-added time / Total manufacturing time
Value-added time in this case is the time spent actually working on the order, which is the sum of the times for cutting, drilling, machining, and assembly:
Value-added time = 1.5 + 0.8 + 0.6 + 1.2 = 4.1 hours
Total manufacturing time is the sum of the value-added time and the non-value-added time (i.e. time spent waiting or in transit):
Total manufacturing time = 4.1 + 1.5 + 0.6 = 6.2 hours
Using these numbers, we can calculate the MCE:
MCE = 4.1 / 6.2 ≈ 0.26
Therefore, the closest answer is C) 0.26.
Learning Objectives
- Acquire knowledge on the concept and calculation of manufacturing cycle efficiency (MCE).
Related questions
Simkin Corporation Keeps Careful Track of the Time Required to ...
Simkin Corporation Keeps Careful Track of the Time Required to ...
Navern Corporation Manufactures and Sells Custom Home Elevators ...
Hunt Company Has the Following Production Data: the Manufacturing ...
During the Most Recent Month at Schwab Corporation, Queue Time ...