The first-stage allocation in an ABC system is the process of assigning functionally organized overhead costs derived from the company's general ledger to activity cost pools.

First-Stage Allocation

The process by which overhead costs are assigned to activity cost pools in an activity-based costing system.

ABC System

The Activity-Based Costing system that assigns manufacturing overhead costs to products in a more logical manner by taking into account the specific activities that incur costs.

Activity Cost Pools

Groups of related costs that are associated with particular activities, used in activity-based costing.

  • Comprehend the methodology behind establishing and executing an Activity-Based Costing (ABC) framework, including the initial and subsequent allocation phases.
verifed

Verified Answer

NM
Nauman MazharMay 25, 2024
Final Answer :
True
Explanation :
The statement accurately describes the first-stage allocation process in an ABC system.